The Brief
We require two classroom spaces, toilets and a break out room please, and it must look the same as our other buildings'
And one more thing....
'All works must be carried out in school summer holidays'
Don't forget.
'The existing building needs demolishing before you can start any works'
The Solution
Hawker Modular used one of our standard twin classroom designs as a starting point, added the break out room and moved the toilet.
A plan was developed to allow time for the school to remove existing teaching equipment prior to demolition. Foundation, drainage and service were installed and the new building delivered.
With good planning and communication all works were carried out during the school holidays as planned, and on budget.
TESTIMONIAL
Having been involved with several modular and traditional build projects over the years I can confidently say that Hawkers and particularly the Project Manager Andrew Caley provided a service unequalled by any other contractor I have worked with.
Their Knowledge, professionalism and dedication to quality were far in excess of what I could have reasonably expected. I very much look forward to working with them on our next project
Trust Estates Manager